Project
Argent Architects Log:
17 May 2010 Grand Designs Catch
The Action
Busy day. With several other events
occuring in the background such as carpenters fixing suspended floor
joists, electricians and lighting designer consulting with Argent
Architects. The Horan Engineering team did extremely well to lift
the waste storage tank and the balcony steelwork in time against
the odds. All of the actions where caught on camera by Grand Designs,
which can be viewed at a later date. |